A practical guide to drafting a verifiable price formula and applying it to purchase orders and invoices without double counting costs. Prepared and legally checked on 29 November 2026.

Coils of steel wire stacked in an industrial storage yard

What decision comes before accepting a price increase?

A supplier of metal coils requests an increase under a three year agreement after a key input becomes more expensive. The buyer has confirmed orders, stock valued at the agreed price and customer quotations it cannot immediately revise. Before negotiating a percentage, procurement needs to know which component of the unit price moves, how the clause treats confirmed orders and when the new amount applies. The supplier needs to know who carries volatility until the next review and what evidence supports the adjustment. A formula agreed in advance lets finance estimate the effect on margins and assess when continuity of supply justifies accepting a price change during the next quarter.

How does Saudi law distinguish applying a formula from amending the contract?

Article 94 of the Civil Transactions Law provides that a valid contract may be amended by agreement or pursuant to a statutory provision. Article 95 requires parties to perform it in accordance with its terms and in good faith. For a sale, Article 313 permits a price to be established by a suitable basis of determination. Applying an agreed formula within its limits and procedures is performance of the contract, provided the inputs yield a calculable amount. Replacing weights, caps or the reference series outside the agreed mechanism requires a separate basis. Where the arrangement includes bespoke manufacturing or services, examine how the relevant commitment is characterised and which special rules apply. Set precedence between the pricing schedule and routine purchase orders so different document formats do not inadvertently change the clause.

How should the parties select and validate an index?

Separate fixed costs from the input to be indexed. If metal accounts for 40 percent of the unit price, record that weight and identify the publisher, exact series, available series code, geography, currency and frequency. A subseries of the General Authority for Statistics wholesale price index may be suitable if it matches the input. Compare its historical movement with the supplier’s cost, particularly where the input is imported and the domestic index covers a broad basket. Check whether freight, duties or currency movements are already reflected, to avoid counting the same cost twice. Define the base month and observation month, and decide which releases and revisions to use. Provide for rebasing, replacement or interruption of the series and say which provisional price applies and how it will be reconciled.

How does the cap work in a reproducible example?

Assume a base price of SAR 1,000 before tax and a 40 percent metal weighting. If the index rises from 100 to 112, the indexed input increases by 12 percent. Applied to the full price, this produces a 4.8 percent adjustment, or SAR 48. An agreed ceiling and floor of 3 percent either side of the base price yield a revised price of SAR 1,030. If the series falls to 90, the theoretical reduction is SAR 40, limited by the floor to a price of SAR 970. The example assumes a limit measured against the original base price with no carryover. A different contract may cap the change for each cycle or each year. Run the calculation in both directions and compare results with the counterparty.

When does the new amount apply to orders and invoices?

Assume quarterly review on 30 days’ notice with a publisher extract, calculation and proposed effective date. Choose a provable event, such as order confirmation or delivery, that fixes the applicable price. Where confirmation locks the price, specify how buyer requested rescheduling and supplier delay affect it. Give accounts payable a way to match invoices covering deliveries on both sides of the date to the underlying order or delivery record. If the index is released after the cycle begins, specify the provisional price and how any adjustment and supporting accounting document will be issued. For disputes, define how the undisputed amount is paid and when the remaining amount must be reviewed, subject to contractual and statutory rights.

When can the statutory hardship provision support negotiations?

Article 97 applies where unforeseeable exceptional circumstances of a general nature make performance onerous enough to threaten the obligor with grave loss. In those circumstances the obligor may invite negotiations without unjustified delay. The request does not entitle the obligor to suspend performance. If no agreement is reached within a reasonable period, the court may reduce the onerous obligation to a reasonable level after weighing both interests. An agreement contrary to Article 97 is void. Ordinary volatility or margin erosion alone is insufficient. Compare the event with the risk already allocated by the contract. Preserve purchase prices, dates, total cost, margin evidence and mitigation efforts to support a fact based review. Assess statutory hardship separately from the routine index mechanism and from any claim concerning impossibility of performance.

What can the parties do if the shock exceeds the cap?

Agree whether the formula price continues during review, subject to statutory rights. A defined cap may sit alongside early negotiations for a prospective rate, an agreed product specification change where permissible or an orderly contractual exit if agreement proves impossible. Where the input can be hedged or bought ahead, compare a shorter price lock with the cost of pricing the risk into a longer commitment. Address any overlap between the benefit of a hedge and the proposed increase. During a dispute, separate disagreements over the series or arithmetic from the legal basis for changing the price. An independent reviewer can check calculations within a defined remit and confidentiality terms. Refer any legal dispute through the agreed process and record the orders and periods covered by an eventual settlement.

Is a supplier invoice enough to establish an increase?

An invoice may show a rise in one supplier’s purchase cost. Under an independent index clause, the adjustment follows the specified series, weight and effective date. Where verified costs can be passed through, check the invoice against rebates, freight, batch records and the amount qualifying under the clause. Define proportionate audit rights and protect confidential data the buyer does not need.

Can the price fall after a previous increase?

It can if the formula is symmetrical and defines the comparison point for each review. Determine whether the reference is the original or current price and verify the order of applying the floor, cap and carryover. Have both teams apply the example to three cycles in which the index rises, falls and then stays flat. This will show whether the clause produces the results intended in each cycle.

Conclusion

A usable price review lets procurement and finance reproduce the result from known inputs. Set the series, weight, observation period, cap and effective date, then test a live order, an invoice spanning the change and a missing index release. Where the requested increase exceeds what the clause permits, identify the legal basis and negotiation route before invoicing at the disputed figure. This keeps the decision auditable and supports continuity while the parties resolve the issue.

For more information, contact us

We help procurement teams and suppliers draft price review provisions and resolve disputes over their application. https://www.azp.sa/en/contact

More insights

Articles and legal updates.

Contact

Speak to AZ&P about the decisions that shape ownership, growth and risk.

Talk to us about your legal matter.

Message us on WhatsApp, call us or book a time. We reply with the next step and a fee quote.