Interim construction certificates | Preventing payment disputes from accumulating
Control valuation, deductions and retention while isolating disputed amounts.

A contractor stops paying suppliers after two monthly applications are returned because one item is disputed. The contract can set a measurement and certification cycle, response deadlines, the effect of silence and a route for paying undisputed sums. Give every deduction a stated reason, amount and basis. Track set-offs, advance recovery, retention and release dates. Define how certification affects the final account and distinguish provisional valuation from acceptance of the works. In a dispute, reconcile quantities with measurement records, invoices and transfers. Isolating recurring disputes helps parties address them early and assess whether the contract permits suspension or other remedies after its conditions are met.