Engineering, Procurement and Construction Contracts: Testing the Lump Sum, Security and Liability Caps
A decision guide to comparing Saudi EPC bids where performance tests, guarantees and liability limits allocate the same project risks differently.

When is a lump sum bid ready for approval?
A developer requests a single bid for the engineering, procurement and construction of an industrial facility. The cheapest bidder offers a lump sum and a firm date but postpones production capacity testing until permanent power arrives and caps delay damages below the cost of lost revenue. A competitor charges more, provides longer security and defines a retest window. The commercial decision is how much exposure remains after the contract allocates risk. Compare the bids against the same operating assumptions and model the cost of delayed connection, failed testing or contractor default. The approval team needs to know who funds a fix, who controls retesting and when accepting reduced capacity or terminating becomes commercially viable.
What assumptions support the lump sum?
Turn each material pricing assumption into a proposition the contract can verify. Specify the temperature at which performance is measured, feedstock characteristics, dates for utilities and the operating envelope. Identify information the contractor may rely on and what it is required to verify. Clarify how quantities will be measured for elements still being designed. For a works contract based on an agreed design at a lump sum, Article 471 of the Civil Transactions Law addresses ordinary increases in cost, design amendments and exceptional circumstances of a general nature that undermine contractual equilibrium. It identifies when design changes can support an increase and the relief available to the court in the circumstances specified. Review the contract’s legal character, pricing documents, provisional items and allocation of input cost risk together.
How does financial security differ from a duty to remedy defects?
A guarantee supports an obligation up to an amount and is callable within the requirements of the instrument. The construction agreement defines the contractor’s duties to remedy, test and bear costs. Check the beneficiary, amount, expiry, call documents and reduction provisions. Link any decrease to verifiable evidence such as a passed performance test and delivery of the records. Distinguish recovery of the advance from general performance security. If acceptance slips, check extension obligations and the practical notice deadline before expiry. Specify when the rectification period begins and how replaced components are treated. Confirm whether the developer can take the benefit of manufacturers’ warranties. These can restrict operating hours or impose servicing conditions that differ from the main contract. Compare both sets of terms to identify periods with insufficient coverage.
When does a failed test become a commercial decision?
Assume a line reaches 90 percent of guaranteed production. The owner needs a minimum threshold compatible with safe operations and debt service and a basis for negotiating acceptance at lower capacity. The contractor needs reproducible test conditions, access to data and time to fix the problem. Allocate retest costs, calibration and responsibility for electricity and materials. Distinguish physical completion from operating acceptance and tie each certificate to payment, insurance, care of the works and spare parts. If conditional acceptance is viable, specify when performance damages are due and whether correction remains required. A shortfall that makes the asset unsuitable for its intended use needs a route for rejection or termination and handover to a replacement contractor.
How should the parties test the liability cap before signing?
Start with a realistic loss scenario combining six weeks of delay and one failed capacity test. Add remedial costs, interim operations and the effect on revenue. Identify what falls under the aggregate cap, any sublimits, insurance or a primary duty to repair, and check for duplicate recovery of the same loss. Article 173 permits agreement on exemptions for contractual nonperformance or delay within limits. It excludes the debtor’s fraud or gross fault and prohibits exemption from liability arising from a harmful act. Articles 178 and 179 govern agreed compensation, including the absence of loss and the conditions for judicial reduction or increase. Test the drafting against these provisions and any mandatory sector rules before using an aggregate number for all categories of exposure.
Which statutory protection should be distinguished from the rectification period?
Where the Saudi Building Code implementing regulations apply, Article 29 addresses joint liability of the supervising designer and the constructor to compensate the owner for total or partial collapse and latent defects threatening structural integrity or safety occurring within ten years from issuance of the occupancy certificate, subject to its terms. It also addresses the approved designer’s position if the designer only prepared the design and invalidates exclusions or limits of the specified protection. Classify components and obligations before applying a single period to the facility. Compare a valve defect affecting output with a structural defect threatening safety, taking account of the contract and independent findings. Retain the occupancy certificate, test records and quality files. Identify who notifies the contractor or insurer and who handles urgent mitigation.
How do these risks translate into award conditions?
Prepare a bid comparison table identifying a potential loss, who bears it, the coverage and evidence needed. Invite each bidder to price the same assumptions for unfinished specifications, with a provisional amount or measurement basis where appropriate. Link changes to a scope record, valuation, programme and test, and have the authorised person approve them before work starts. Rehearse an acceptance day on which payment and release of part of a guarantee are requested while a defect remains. The project team should be able to identify the party that issues the certificate, the residual security and when it can demand rectification. Record remaining owner exposure, allowances and named owners in the investment approval. Run a separate liquidity test. Assume that 90 percent of the price falls due on physical handover, capacity is proved two months later and the instrument expires midway through that period. Identify how much the contract allows the owner to retain, when the beneficiary should request an extension and whether supplier invoices fall due before the test passes. The answers may change the award decision even where all bids offer the same headline security percentage.
Does delivery of the plant reduce the bank guarantee?
Read the instrument and contract and identify the certificate or event that triggers a reduction. Physical handover may occur before operating acceptance or complete delivery of records. Compare the trigger with remaining risks before authorising a reduction. If the handover and test dates differ, apply the event specified for each instrument and document its extension or replacement before the right to call expires.
Do delay and performance damages consume the same cap?
The aggregate and separate cap terms determine how each claim is counted and whether amounts accumulate. Model delay, capacity shortfall and repair cost together. Check mandatory exceptions and avoid counting the same loss twice. Recording the result gives both parties a basis for changing a limit or negotiating additional security for exposure outside the proposed coverage.
Conclusion
Test an EPC bid against the exposure that remains with the project after contracting. For price changes, failed tests, defects and delay, identify the decision maker, evidence and available cover. Where the cap and security leave a material gap, and the repair may take longer than the contract allows, review the price or the protection before award. Keep a record that construction, finance and operations teams can use during delivery.