Delay damages in private Saudi construction contracts
Review the completion date, extensions and sectional handover before assessing agreed delay damages.

When an owner deducts delay damages from the final account, start with the adjusted completion date and determine whether the clause covers the delayed section. Review Article 178 of the Civil Transactions Law on agreeing damages in advance and Article 179 on proof of no loss and possible reduction, including for excessive assessment or partial performance. An increase may be relevant where the statutory conditions are met. Check any extension, sectional handover, daily rate and cap. Document the works covered, days counted and correspondence affecting the calculation. For government contracts, review the applicable public procurement rules on penalties and the terms of the particular contract.
For more information, contact us.