Defective construction | When can another contractor carry out repairs?
Use documented notice, inspection and a cure process before engaging a replacement contractor.

If waterproofing fails before completion, immediate repair can make its cause and cost harder to prove. Record the location, drawings, photographs and test results, and distinguish a design problem from defective workmanship. Review Article 466 of the Saudi Civil Transactions Law and the contract on notice, cure periods, engaging a replacement and possible termination, as applicable. Where damage may worsen, separate urgent protective measures from permanent rectification and record why each was needed. If another contractor is engaged, distinguish necessary repair from betterment in the quotations and invoices. Preserve records of areas covered or removed so the original contractor’s responsibility and the claimed amount can be assessed.